KBH Construction Update

Martin Jahn Nursing Pavilion

Gardens Level

  • Painting and carpeting will be finished by the end of this week
  • The pre-punch list will be developed by Pepper.
  • The mechanical, electrical and plumbing punch list will be developed next week.
  • Crown molding and siding for the columns will be installed on the Porte cochere this week and next.

1st floor

  • Trim and painting will be finished next week.

The Gardens

  • ComEd came out and are pulling cable for the new building.
  • On Thursday or Friday of this week, the North slab on grade will be poured.
  • Drain tile along the exterior foundation walls will be installed and then dirt will be backfilled around the tile.