• Last Wednesday over 100 of yards of concrete was poured for The Gardens’ walls. The concrete team is busy this week framing up for additional walls which will be poured very soon.
  •  The footings and concrete walls for The Gardens should be finished  in approximately 2-1/2 months.
  •  All tile work for bathrooms in the garden level of the new skilled nursing building is complete and they are still working on the 1st floor. Also, flooring in some residential suites has been installed.
  •  Exterior work continues at skilled nursing as white siding (similar to that on the Manor Home) is being installed.